PROJECT STATUS

Segment C and North 101 Drainage Improvements, between Jupiter Street and La Costa Avenue, began construction in March 2024 with anticipated completion expected in summer 2026.

Tree removals have occurred and work along the medians is underway.  Excavation and installation of new 60-inch storm drainpipe began at Jupiter Street and will continue northward to Moorgate Road.  The next line of work will be replacement of the water line on the west side of N. Coast Hwy 101.  Installation of surface storm drains will be occurring throughout the project length.

Expect traffic control with intermittent lane shift, along with construction related activities and impacts including noise, dust, lighting, and large construction vehicles.  Access to driveways and businesses will be maintained.  Please support our local Leucadia businesses during construction.

View our Frequently Asked Questions (FAQs) for Segment C West to learn more about the project.

Streetscape Segment C West FAQ's - General
Streetscape Segment C West FAQ's - Businesses
Streetscape Segment C West FAQ's - Trees

  • Segment C - (Jupiter St. to La Costa Ave.) Bicycle and Pedestrian Enhancements, Pavement Improvements, Wider Sidewalks, Designated Bike Lanes, New Roundabouts at Jupiter St. and Moorgate Rd., New Streetlights, Crosswalks and Ped Signal at Avocado St., New Benches, Bike Racks and Hundreds of New Trees.
    Segment C West (Jupiter to La Costa)
    Project Renderings
    Project Timelines
    Click here to view on City Projects Dashboard
  • North 101 Drainage Segment C - (Jupiter St. to La Costa Ave.)                 
    New Drainage Infrastructure to Reduce Flooding and Provide Stormwater Treatment
    Segment C West Drainage (Jupiter to La Costa)
    Click here to view on City Projects Dashboard

    On June 12, 2024 City Council approved additional funding to complete the 60-inch drainage work for the project between Jupiter St. and La Costa Ave.  The additional funding and project scope will extend the construction timeline, with a new completion target date of summer 2026.

Segment C Business Maps

Updated on 06/14/2024 11:39 AM

Please support our local businesses during construction.

About the Project
Completed Segements
Future Segments
Past Actions
Image of Pavement improvements
Image of Median improvements
Image of west side sidewalk improvements